INFORMATION OF ELECTRICITY NETWORK RELIABILITY IMPROVEMENT PT. PLN (PERSERO) UP3 BANYUWANGI |
||
---|---|---|
Day / Date | : | Thursday, 30 January 2020 |
Jam | : | 09:00 - 13:00 WIB |
Location of Padam | : | Ds. Tampo, Ds. Plampangrejo, Ds. Kradenan, Ds. Kaliboyo, Ds. Kaliploso, Dn. Simbar, Dn. Kopen, Dn. Rumping, and surrounding |
Profession | : | Pemasangan Konstruksi dan Pemasangan LBS (Load Break Switch) Randu pada Jaringan SUTM (Medium Voltage Air Line) 20.000 Volt - Penyulang Sumberayu & Penyulang Purwoharjo |
Work Area | : | PLN Unit Layanan Pelanggan Rogojampi |
When the job is finished before the hour 13.00 WIB, then the flow of electric power will be normalized again. | ||
When it comes to the clock 12.00 WIB there is no blackout, means the blackout is cancelled. | ||
Source : https://www.facebook.com/plnup3banyuwangi/, For information or service complaints, please go directly to the PLN Contact Center 123 or through the PLN MOBILE application. |